Construction activities are officially underway on the second phase of Williams’ Hillabee Expansion project.
Initial construction activities have included contractor mobilization, environmental training and site preparation at the location of a nearly seven-mile pipeline loop (known as the Rock Springs Loop) planned in Choctaw County, Ala. Work on the nearly four-mile Verbena Loop in Chilton County, Ala., is scheduled to begin in April.
Williams successfully placed the first phase of the Hillabee project into service in July 2017, expanding its Transco pipeline’s capacity in Alabama by 818,410 dekatherms per day to supply Florida power generators via the new Sabal Trail pipeline.
The project was approved by the Federal Energy Regulatory Commission (FERC) in February 2016.